Clinton County supervisors and the conservation board directed engineers to draw up dredging plans and cost estimates for the Rock Creek slough, which has silted up and become too shallow for many boats. Engineers estimated dredging a 6-foot channel at 45, 60 or 90 feet wide would cost $1.2 million to $2.4 million.
The project must also be coordinated with the U.S. Army Corps of Engineers because the marina sits on federal land.