Centrex Metals said it visited CDE Global's facilities as part of a client review for detailed design of a 70 tph startup wet processing plant at its Ardmore Phosphate Rock Project in Queensland. The startup plant is planned to produce phosphate rock for trial shipments in 2019.
Feasibility studies, mine designs and cost estimates are progressing, with cost estimates due at the end of August.
Ardmore is a development-stage project, so it adds no near-term phosphate rock supply, but its planned 800,000 tpy output could add supply later in the decade.