Latrobe Magnesium said it has finished installing its Phase 1B pyrometallurgical stage at its Latrobe Valley Demonstration Plant in Victoria. Staged commissioning has reached 78%, up from 50% at October 31, and furnace heating has begun.
The company remains on track to produce magnesium metal crowns by the end of 2026 within its A$6.1 million budget.